Construction of a state of the art facility incorporating a 4m deep dive pool, board and training rooms, highly appointed retail fit out, administration offices, amenities and multiple utility rooms. 

 The project finishes were highly complex as were the water proofing systems and structural engineering; relying on seventy two steel screw piles supporting two suspended floor levels. Field Construct worked to overcome many obstacles such as recieving the largest historical Port Douglas rain event (593mm in 24hrs) which floated our site offices down the road.

We're very pleased with the quality of work and the attention to detail provided by Field Construct; in addition we're impressed that a project of this complexity was completed in such a timely manner.

 

Tony Baker - Managing Director

 