CAIRNS HAEMATOLOGY & ONCOLOGY DAY CLINIC

Cairns Haematology & Oncology Day Clinic

The recently completed Cairns Haematology & Oncology Day Clinic Fitout is a significant demonstration of Field Construct's ability to interpret and facilitate client objectives into the project management plan.

The client was eager to commence services as soon as possible and requested completion of consturctions within 10 weeks of commencement. The construction phase was scheduled over the Christmas shutdown period, which traditionally presents challenges to the procurement of materials and coordination of trades. 

Field Construct's team took a proactive approach to trade letting and material ordering immediately upon contract issue, enabling orders to flow before the supply chain shutoff date.

The result was a project that was delivered two weeks ahead of programme, exceeding the client objective and enabling the clinic to open and take patient referrals well ahead of schedule.

Project Gallery